Review planned work in a Gantt view
Map the start and end dates, compare scheduled work on a timeline, and check records whose bars are missing.
Set up the timeline
- Open a table under Tables and select View → Gantt. If Gantt is unavailable, check that the table supports this view and has compatible start and end date options. A date-range field can supply both options.
- Open View options and set Start date and End date. For a table with a Planning range, choose Planning (Start) and Planning (End). If your table has separate fields, choose the two that describe the schedule you want to review.
- Find the period you need. Use the zoom controls to see individual days or to compare work across a longer period. Use the calendar icon to return to today.
- Compare the bars to see which work is scheduled at the same time. Open a record and check its dates if a bar starts or ends somewhere unexpected.
If both selectors show Created At, set them to your planning dates before reviewing the schedule. For example, use Planned start and Planned finish to compare delivery dates across projects.
Check missing or unexpected bars
- Check the date fields selected in View options and the active table filters.
- If a record is missing, switch to Table, find the record, and check that both selected dates are filled in. Return to Gantt and navigate to the period those dates overlap.
- If the dates and filters match, check the record pages at the bottom of the view. Next there loads another page of records. Use the timeline’s date controls to change the period.
Move work or change its duration
- Check that the date selectors point to the planning fields you want to change. Moving or resizing a bar updates the corresponding dates on the record when you release it.
- Drag the body of the bar to shift both dates and keep its duration. Drag the handle at the end of the bar to change the end date while keeping the start date.
- Open the record and check the fields selected in View options to confirm the saved dates.
If you can open a bar but can’t move it, check whether you can edit that record. Bars in virtual tables are read-only in Gantt.
Save the view if you want to reopen the same date mapping and filters later.
To review records in order by one date field, use Timeline.
Ask Mainbase AI
Ask about any feature in Mainbase. Find a setting, get step-by-step guidance, or troubleshoot a problem.