Plan a project’s child records in Gantt
Open Gantt from a parent record, compare the dates of its child records, and check the schedule after a change.
Use Gantt on a parent record when you need the schedule for one project or another parent. For example, open a project to compare the planned dates of the requests under it.
Open the parent’s planning view
- Open the parent record’s full page. In Related Records, choose the tab named for the table, such as Requests. If the tab has more than one connection, use Connection type to choose the records you want to plan.
- On that tab’s toolbar, choose View → Gantt. If Gantt is missing, check whether the child table supports Gantt and has suitable start and end fields.
- Under View options, map Start date and End date to the child records’ planning fields. For example, use the start and end of a Planning date range. If the tab has filters, check that they include the children you want to compare.
Plan the right period and verify a change
- Use the scale menu to choose the detail you need. Weekly shows the month in weeks. Daily shows the week in days. Changing the scale returns the view to the period that contains today, so choose your scale before moving to your target period.
- Use the arrows beside the date range to reach the planning period. When an empty period offers Jump to first item, use it to find the earliest start on the current page of records. Check another record page if the child you need is missing.
- To move one child’s dates, select its bar to check the record, then move or resize the bar if you can edit it. Reopen the child and verify its saved start and end dates. Review other affected children individually when the schedule changes.
Ask Mainbase AI
Ask about any feature in Mainbase. Find a setting, get step-by-step guidance, or troubleshoot a problem.
Open the AI assistantCopy a question to get started
- How do I create a Kanban view?
- How do I invite a teammate?
- Why is a record missing from this view?